Free UK RAMS template, in Word and PDF

A blank risk assessment and method statement for one job, ready to fill in digitally in Word or print as a PDF. There is also a filled-in example, a consumer unit replacement in an occupied house, so you can see what good answers look like.

What is a RAMS?

A RAMS (risk assessment and method statement) is the health and safety document for one job. The risk assessment sets out what could hurt someone, who, and how you will control it. The method statement sets out how the work will be done, step by step, with those controls in place.

Principal contractors commonly ask for one before you start on their site, and so do many clients, facilities managers, venues, event organisers and film and TV productions. Some will not let you start until they have read it.

The legal duty behind it is the risk assessment. Regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires a suitable and sufficient assessment of the risks, and an employer with five or more employees must record its significant findings. The duty also covers self-employed people working in construction or whose work could put others at risk.

A method statement is not usually required by law under that name, but it is a common condition of getting on site. On construction work, including domestic jobs, CDM 2015 also requires contractors to plan, manage and monitor their work, and a RAMS is a common way to show that planning.

Risk Assessment and Method Statement (RAMS)

What’s in the template

  1. Job details

    Where the work is, who it is for and when it happens.

    • Job title
    • Client
    • Site address
    • Principal contractor
    • Dates and working hours
  2. Document control

    Who wrote this RAMS, which version it is and when it will be looked at again.

    • Company
    • Prepared by
    • Date and revision
    • Review date
  3. Scope of work

    A plain description of what will and will not be done. Someone who has never been to the site should understand the job from it.

    • Description of the work
    • Not included
    • Related documents
  4. People and competence

    Who will do the work, why they are competent to do it safely, and who else could be affected.

    • Person in charge on site
    • Team
    • Qualifications, cards and training
    • Others affected
  5. Site and access

    Conditions at the place of work that change how the job is done safely.

    • Access and parking
    • Site conditions and known hazards
    • Asbestos
    • Keeping others out
  6. Plant, tools and materials

    Everything brought to site for the job, and any substances that need a COSHH assessment.

    • Plant and tools
    • Materials
    • Hazardous substances (COSHH)
  7. Personal protective equipment (PPE)

    PPE is the last line of defence. It is worn as well as the controls in the risk table, not instead of them.

    • Worn at all times
    • For specific tasks
  8. Permits and isolations

    Formal permissions, and how energy and services are made safe before work starts.

    • Permits required
    • Isolations
    • Notifications and consents
  9. Emergency arrangements

    What happens if someone is hurt or something goes wrong. Everyone on the job should know this before work starts.

    • First aid
    • Nearest A&E
    • Fire
    • Emergency contacts
    • Accident and near miss reporting
  10. Welfare

    Toilets, washing facilities, drinking water and somewhere to take a break. CDM 2015 requires these on construction work.

    • Welfare arrangements
  11. Environment and waste

    How the job avoids harm to the surroundings and deals with its waste properly.

    • Waste
    • Noise, dust and pollution
  12. Toolbox talk

    Everyone who works to this RAMS is briefed on it before work starts, and again if it changes. Each person then signs the briefing register at the end of this document.

    • Briefed by, date and time
    • Points covered
  13. Risk assessment

    List each significant hazard for this job and who could be harmed. Score it before controls: likelihood (1 rare, 2 unlikely, 3 possible, 4 likely, 5 almost certain) times severity (1 negligible, 2 minor, 3 moderate, 4 major, 5 catastrophic, meaning death or permanent disability). Write the controls you will actually use, then score it again. 1 to 4 is low, 5 to 9 medium, 10 to 16 high, 17 to 25 critical. If a risk is still high or critical after controls, change the method or add controls before work starts.

  14. Method statement

    Write the work as numbered steps in the order it will be done, from arrival to handover. For each step, say who does it, how, and which controls from the risk table apply at that point. Include setting up, isolations, checks and tests, and leaving the site safe.

  15. Sign-off and briefing register

    Who prepared and approved the RAMS, with a signature and date for each, then a register for everyone briefed on it to sign.

  16. Risk scoring key

    The 5 x 5 grid used to score each risk: likelihood times severity gives the score and its level.

Worked example

Consumer unit replacement in an occupied house

Open the example as a PDF

Risk Assessment and Method Statement (RAMS)

Job title
Consumer unit replacement, 22 Fernhollow Road
Client
Mrs Ruth Ellery, homeowner. She is at home on the day and is the contact for any questions.
Site address
22 Fernhollow Road, Northampton. 1960s semi-detached house. The consumer unit and the meter are in the cupboard under the stairs, next to the front door.
Principal contractor
None. Domestic job with Kilnbrook Electrical as the only contractor, so a one-page construction phase plan is kept with this RAMS.
Dates and working hours
14/10/2026, one day, 08:30 to 16:30. Power off from about 09:30 to 15:00, agreed with Mrs Ellery.

Risk assessment

HazardWho might be harmedInitial riskControl measuresResidual risk
HazardElectric shock or electrocution from live parts while removing and connecting the consumer unit, including the tails between the meter and the isolator, which stay liveWho might be harmedOwen and Jay; the occupants if live parts were left exposedInitial risk15 Highlikelihood 3 × severity 5Control measures
  • Supply isolated at the double-pole isolator switch, locked off with Owen's personal padlock and a danger tag. Owen keeps the only key.
  • Dead proved at the consumer unit with an approved voltage indicator meeting HSE guidance GS38, checked on a proving unit before and after, between every combination of line, neutral and earth.
  • Checked at the quote visit and again on the day: no solar panels, battery storage or generator that could feed the house.
  • The meter, the network operator's cut-out and the tails up to the isolator are treated as live and not worked on.
  • Only Owen isolates, proves dead and re-energises. Jay works under his direct supervision and never on the board alone.
  • Nobody works on live conductors (Electricity at Work Regulations 1989). The only live work is testing, done by Owen with GS38 leads and probes after the dead tests are satisfactory.
Residual risk5 Mediumlikelihood 1 × severity 5
HazardAsbestos fibres released by disturbing the old fuse board, its backboard, the pads in the fuse carriers or the wall behindWho might be harmedOwen, Jay and the occupantsInitial risk15 Highlikelihood 3 × severity 5Control measures
  • Backboard and fuse carrier pads sampled by a competent asbestos surveyor on 06/10/2026. The accredited laboratory found no asbestos (result kept with this RAMS).
  • Old board removed in one piece, not broken, cut or drilled.
  • If any other suspect material is found, such as a fibre board or lining behind the old board: stop, keep everyone away, do not disturb it, and have it sampled before carrying on, in line with the Control of Asbestos Regulations 2012.
  • Owen and Jay both hold in-date asbestos awareness training.
Residual risk5 Mediumlikelihood 1 × severity 5
HazardOccupants, a young child or the dog coming into the work area: contact with open equipment, tools or sharp offcuts, or the dog getting out through the front doorWho might be harmedMrs Ellery, her son (aged 4), the dog and visitorsInitial risk12 Highlikelihood 3 × severity 4Control measures
  • Agreed with Mrs Ellery on arrival that her son and the dog stay out of the hall while work is under way.
  • Cupboard door kept closed, or one of the team stays at the cupboard, whenever the board is open.
  • Covers and blanks fitted before the team steps away, so nothing is left exposed.
  • Tools, blades and offcuts kept in the cupboard or the tool bag, never on the hall floor.
  • Front door kept shut between trips to the van.
Residual risk4 Lowlikelihood 1 × severity 4
HazardLoss of power to the house for about five and a half hours: heating, fridge-freezer, smoke alarms, home working, and anyone relying on powered medical equipmentWho might be harmedMrs Ellery and her sonInitial risk9 Mediumlikelihood 3 × severity 3Control measures
  • Confirmed at booking that nobody in the house relies on powered medical equipment.
  • Power-off times agreed in advance (about 09:30 to 15:00), and Mrs Ellery reminded on arrival.
  • Fridge-freezer kept shut while the power is off.
  • Mains smoke alarms have backup batteries (checked at the quote visit), and every alarm is tested once the power is back on.
  • Boiler, heating timer and clocks checked and reset with Mrs Ellery at handover.
  • If a circuit cannot safely be switched back on, the reason is explained to Mrs Ellery and the rest of the house is put back on.
Residual risk3 Lowlikelihood 1 × severity 3
HazardManual handling: lifting out the old board and holding the new steel consumer unit in place while kneeling in a cramped cupboardWho might be harmedOwen and JayInitial risk6 Mediumlikelihood 3 × severity 2Control measures
  • Two people to put the new unit in place: one holds it while the other fixes it.
  • Kneeling mat, and short breaks out of the cupboard.
  • Battery work light, so nobody has to stretch or twist to see.
  • Old board carried straight out to the van, not left in the hall.
Residual risk4 Lowlikelihood 2 × severity 2
HazardDust from drilling fixing holes in brick and plaster, including silica dust, and debris in the eyesWho might be harmedOwen, Jay and the occupants nearbyInitial risk9 Mediumlikelihood 3 × severity 3Control measures
  • Only the fixing holes the new unit needs, drilled with a dust extraction attachment connected to an M-class vacuum.
  • Disposable FFP3 mask (face-fit tested) and safety glasses while drilling.
  • Family kept out of the hall while drilling.
  • Cleaned up with the vacuum, never by dry sweeping.
Residual risk3 Lowlikelihood 1 × severity 3
HazardFire or burns from overheated connections, arcing when the supply is restored, or a poorly made termination in the new unitWho might be harmedThe occupants, Owen and JayInitial risk10 Highlikelihood 2 × severity 5Control measures
  • New consumer unit has a non-combustible steel enclosure, as BS 7671 requires for consumer units in homes.
  • Every terminal tightened to the manufacturer's torque setting with a torque screwdriver, and every conductor checked for correct insertion.
  • Cable entries made with the manufacturer's fittings, and any gaps sealed with fire-rated sealant.
  • Isolator, tails and cut-out checked for signs of overheating before work starts. Any damage to the network operator's equipment is reported to them on 105 and not touched.
  • Dead tests completed and satisfactory before the supply is restored, then circuits switched on one at a time.
  • CO2 extinguisher kept at the cupboard during the work.
Residual risk5 Mediumlikelihood 1 × severity 5
HazardSlips, trips and falls over tools, cables, dust sheets or the old board in the hall and on the stairsWho might be harmedOwen, Jay and the occupantsInitial risk6 Mediumlikelihood 3 × severity 2Control measures
  • Cordless tools and a battery work light, so there are no trailing leads.
  • Dust sheets laid flat in the hall, and none on the stairs.
  • Hall and stairs kept clear at all times.
  • Waste and packaging taken out to the van as it is produced.
Residual risk2 Lowlikelihood 1 × severity 2

Likelihood × severity

Low 1–4Medium 5–9High 10–16Critical 17–25

Method statement

  1. Arrive and brief the household

    Arrive at 08:30 and park on the drive. Owen briefs Jay on this RAMS and both sign the briefing register. Owen then goes through the day with Mrs Ellery: power off from about 09:30 to 15:00, her son and the dog kept out of the hall, nothing to be switched on or off at the board, and the fridge-freezer kept shut. Lay dust sheets flat in the hall.

  2. Check the existing installation and the asbestos result

    Before isolating, look over the isolator, the tails and the network operator's cut-out for damage, overheating or a broken seal. If any is found, stop and report it to the network operator on 105. Confirm again that there are no solar panels, battery storage or generator. Check the board and backboard are the ones sampled on 06/10/2026, and stop if any other suspect material is found (risk 2). Note what each circuit feeds, and check the main earthing and the main protective bonding to the gas and water pipes, which BS 7671 requires to be adequate for the new work. If either falls short, agree with Mrs Ellery how it will be put right before the new board goes into service.

  3. Confirm where the supply is isolated

    This house has a double-pole isolator switch between the meter and the fuse board, so the supply is isolated there and the network operator's cut-out fuse is not touched. The cut-out fuse belongs to the network operator. If there had been no isolator, the fuse would have been withdrawn only by the network operator, a Safe Isolation Provider, or by Owen where that network operator's own procedure allows registered electricians to do so, arranged before the job.

  4. Isolate, lock off and prove dead

    Owen switches off the main switch and then the isolator, locks the isolator off with his personal padlock and a danger tag, and keeps the key. He checks the voltage indicator on the proving unit, tests between every combination of line, neutral and earth at the incoming terminals of the board, then checks the indicator on the proving unit again. Work on the board starts only after this.

  5. Test the existing circuits and remove the old board

    Before anything is disconnected, test the insulation resistance of each existing circuit, with sensitive equipment unplugged, and record the results, so faults are found before the new RCBOs are fitted. Tell Mrs Ellery about any fault and what it means for the day. Label each circuit's cables, photograph the connections, disconnect them and remove the old board in one piece. Take it straight out to the van.

  6. Fit the new consumer unit

    Fix the new steel consumer unit in the same position, drilling only the holes needed, with dust extraction (risk 6). Bring the cables in through the manufacturer's entry fittings and seal any gaps with fire-rated sealant. Connect each circuit to its RCBO, connect the earthing conductor and the new tails from the isolator, and tighten every terminal to the manufacturer's torque setting. The work is done to BS 7671:2018+A4:2026, the current IET Wiring Regulations, which require a consumer unit in a home to have a non-combustible enclosure or to be housed in one.

  7. Inspect and test before switching on

    With the supply still locked off, inspect the new work and carry out the dead tests: continuity of the protective conductors and ring final circuits, insulation resistance and polarity. Record every result on the schedule of test results. A circuit that is not satisfactory stays disconnected, and the reason is explained to Mrs Ellery.

  8. Re-energise and complete the live tests

    Fit the covers and switch off every circuit device. Owen removes his lock, switches on at the isolator and then the main switch, and switches the circuits on one at a time. He carries out the live tests (earth fault loop impedance, prospective fault current and RCBO operation) and checks the surge protection device's indicator. Then check that the smoke alarms, the boiler and the fridge-freezer are working.

  9. Complete the Electrical Installation Certificate

    Owen completes an Electrical Installation Certificate for the new consumer unit, with the schedule of inspections and the schedule of test results, and records any defects found on the existing circuits. Mrs Ellery is given a copy.

  10. Notify the work under the Building Regulations

    Replacing a consumer unit in a home in England is notifiable under Part P of the Building Regulations. Owen notifies it through his competent person scheme within 30 days of finishing. The scheme tells the local authority and sends Mrs Ellery a Building Regulations compliance certificate.

  11. Hand over and clear up

    Show Mrs Ellery the new board: the isolator and main switch, what each RCBO feeds, how to use the test buttons as the label on the board explains, and what to do if one trips. Reset the clocks and heating timer with her. Vacuum the cupboard and hall, and take the old board, offcuts and packaging away for recycling.

How to use this template

  1. Download the Word file and save a fresh copy for each job. Do not send the last job's RAMS with the names changed.

  2. Open the worked example alongside it, to see the level of detail to aim for.

  3. Fill in the job details, scope, people and site first, so the hazards you list are about this job, this site and this team.

  4. List the significant hazards in the risk table. Score each one before and after controls: likelihood times severity, each from 1 to 5.

  5. Write the method as numbered steps in the order the work happens, with each control at the point it is needed.

  6. Read it through against the job. Are these the controls you will really use on the day? Delete any guidance text you have not replaced.

  7. Brief everyone who will do the work, have them sign the briefing register, and review the RAMS if the job, the site or the team changes.

Common questions

Is a RAMS a legal requirement in the UK?

Not by that name. The law requires a suitable and sufficient risk assessment (regulation 3 of the Management of Health and Safety at Work Regulations 1999), with the significant findings written down if you employ five or more people. A method statement is not usually a legal requirement in itself, but principal contractors and clients commonly make it a condition of starting. On construction work, CDM 2015 also requires you to plan, manage and monitor the work, and if you are the only contractor it requires a construction phase plan, which can be short for a small job.

What is the difference between a risk assessment and a method statement?

The risk assessment asks what could go wrong: the hazards, who could be harmed, how likely and how serious it is, and the controls. The method statement says how the job will be done, step by step, with those controls in the right places. Together they make the RAMS, and they should agree with each other.

What should a RAMS include?

Job and site details, the scope of work, who will do it and their training, the hazards with their risk ratings and controls, the method step by step, PPE, permits and isolations, emergency arrangements, welfare, waste, a sign-off, and a register of who was briefed. This template has a place for each. Keep it to the job in front of you: a short, specific RAMS is more use than a long, generic one.

Can I use the same RAMS for every job?

Only the parts that really are the same. The site, the people around you, access, emergency arrangements and often the hazards change from job to job, so update them and re-date the document each time. HSE's own guidance warns that copying an example and adding your company name is not enough to meet the law.

Is this RAMS template free, and can I edit it in Word?

Yes. The blank template is a Word file you can fill in on screen, on a computer, tablet or phone, and a PDF you can print and fill in by hand. The worked example is a PDF. There is nothing to buy and no sign-up, and you can use them for as many of your own jobs as you like.

Does HSE provide a RAMS template?

No. HSE publishes a free risk assessment template, in Word and OpenDocument formats, with example risk assessments for a few types of business. It is a general risk assessment, not a RAMS, so it has no method statement, job details or briefing register. This template covers both parts for a single job.