Free UK risk assessment template, in Word and PDF

A blank risk assessment form for one job or activity, ready to fill in on screen in Word or print as a PDF. It follows HSE's five steps, scores each hazard before and after controls, and ends with a sign-off and a register for the team to sign. There is also a filled-in example, replacing gutters and fascias from a scaffold, so you can see what good answers look like.

What is a risk assessment?

A risk assessment is a careful look at what in your work could harm people, so you can decide whether you are doing enough to prevent it. It lists the hazards, who could be harmed and how, how likely and how serious the harm would be, and the controls that bring the risk down.

The law requires one. Regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires every employer to make a suitable and sufficient assessment of the risks to their employees and to anyone else affected by the work. The duty also covers self-employed people working in construction or whose work could put others at risk. An employer with five or more employees must write down the significant findings.

HSE sets out five steps: identify the hazards; decide who might be harmed and how; evaluate the risks and decide on the controls; record your significant findings; and review the assessment, updating it when things change. This template follows those steps for one job, site or activity.

On a construction site you will usually be asked for a risk assessment together with a method statement, the pair known as RAMS. If the job needs both, use the free RAMS template, which has the method statement as well.

Risk Assessment

What’s in the risk assessment template

  1. Assessment details

    What the assessment covers, who made it and when it will be looked at again.

    • Activity or job
    • Location
    • Company
    • Client
    • Assessed by
    • Date and review date
  2. The work

    A plain description of the work, so anyone reading the assessment knows what it covers and what it does not.

    • Description of the work
    • Dates and hours
    • Equipment and substances
    • Related documents
  3. People

    Who does the work, and everyone else who could be harmed by it.

    • People doing the work
    • Others who could be affected
    • People at particular risk
  4. Emergency arrangements

    What happens if someone is hurt or something goes wrong. Everyone doing the work should know this before they start.

    • First aid
    • Nearest A&E
    • Emergency procedures
    • Reporting accidents
  5. Hazards and controls

    List each significant hazard, and who could be harmed and how. Score it before controls: likelihood (1 rare, 2 unlikely, 3 possible, 4 likely, 5 almost certain) times severity (1 negligible, 2 minor, 3 moderate, 4 major, 5 catastrophic, meaning death or permanent disability). Write the controls you will actually use, then score it again. 1 to 4 is low, 5 to 9 medium, 10 to 16 high, 17 to 25 critical. If a risk is still high or critical after controls, change how the work is done or add controls before it starts.

  6. Sign-off and briefing register

    Who prepared and approved the risk assessment, with a signature and date for each, then a register for everyone briefed on it to sign.

  7. Risk scoring key

    The 5 x 5 grid used to score each risk: likelihood times severity gives the score and its level.

Worked example

Risk assessment example: replacing gutters and fascias on a two-storey house

Open the example as a PDF

Risk Assessment

Activity or job
Replacing fascias, soffits, gutters and downpipes, 14 Larchmere Avenue
Location
14 Larchmere Avenue, Chesterfield. 1970s two-storey semi-detached house. Work along the front and the gable end, above the drive and beside the public footpath.
Company
Brookfold Roofline Ltd, Chesterfield
Client
Mr Dev Parmar, homeowner. He is at home most days and is the contact for access, parking and the skip.
Assessed by
Sam Kettle, director and site lead, after a site visit on 04/11/2026 and a talk through the job with the two fitters.
Date and review date
10/11/2026, once the asbestos result was back. Reviewed on site on 16/11/2026 before work starts, and again if the weather, the scaffold or the job changes.

Hazards and controls

HazardWho might be harmedInitial riskControl measuresResidual risk
HazardFalls from the scaffold while working at the eaves, including leaning out past the guardrail or standing on it to reachWho might be harmedSam, Ellie and KofiInitial risk15 Highlikelihood 3 × severity 5Control measures
  • Independent tied scaffold with double guardrails and toe boards on every working lift, erected by the scaffolding contractor and handed over with a certificate before anyone uses it.
  • Scaffold inspected by the scaffolding contractor before first use, at least every seven days and after high winds, and each inspection recorded, as the Work at Height Regulations 2005 require.
  • Nobody removes or alters any part of the scaffold. If a guardrail or tie is in the way, stop and call the scaffolding contractor.
  • Work from the boards only: no leaning out past the guardrail, and no standing on guardrails, buckets or stepladders on the scaffold.
  • Up and down by the scaffold's internal ladder only, with three points of contact and nothing carried in the hands.
Residual risk5 Mediumlikelihood 1 × severity 5
HazardAsbestos fibres released by cutting or breaking the old soffit boards, or any other suspect material found at the eavesWho might be harmedThe team, the family and the neighboursInitial risk10 Highlikelihood 2 × severity 5Control measures
  • Soffit boards sampled by a competent asbestos surveyor on 05/11/2026. The accredited laboratory found no asbestos (result dated 09/11/2026, kept with this assessment).
  • If any other suspect material is found, such as a board behind the fascia or an old cement gutter or downpipe: stop, keep everyone away, do not disturb it, and have it sampled before carrying on, in line with the Control of Asbestos Regulations 2012.
  • Old boards taken down whole where possible, not broken up on the scaffold.
  • Everyone on the job holds in-date asbestos awareness training.
Residual risk5 Mediumlikelihood 1 × severity 5
HazardTools, offcuts or old gutter falling from the scaffold onto people belowWho might be harmedThe family, visitors, people on the footpath, and the team on the groundInitial risk12 Highlikelihood 3 × severity 4Control measures
  • Toe boards and brick guards along every working lift, fitted by the scaffolding contractor.
  • Waste goes down the enclosed chute into the skip, never thrown or dropped.
  • Tools kept in a bucket or tethered on the boards, and nothing left near the edge.
  • Barriers and signs round the base of the scaffold and the skip, keeping everyone but the team out of the area below the work.
  • Agreed with Mr Parmar that the family uses the side door while the team works above the front door.
Residual risk4 Lowlikelihood 1 × severity 4
HazardMembers of the public, children walking to school or the family coming into the work area, climbing the scaffold or walking into the skipWho might be harmedPeople on the footpath, school children, Mr Parmar's family and his motherInitial risk12 Highlikelihood 3 × severity 4Control measures
  • Scaffold and skip kept within the property boundary, so the footpath stays open.
  • Barriers and signs round the scaffold base and the skip at all times.
  • Ladder access to the scaffold blocked with a locked ladder guard at the end of each day and whenever the team is away.
  • No loading or lifting at the front during the school run, about 08:15 to 08:45 and 15:00 to 15:30.
  • Side path kept clear and level for Mr Parmar's mother, and the plan for the week agreed with the family on the first morning.
Residual risk4 Lowlikelihood 1 × severity 4
HazardManual handling of long lengths of fascia board, soffit and gutter, and passing materials up onto the scaffoldWho might be harmedSam, Ellie and KofiInitial risk9 Mediumlikelihood 3 × severity 3Control measures
  • Long lengths carried and passed up by two people, one at each end, never up the ladder.
  • Materials passed up through the scaffold's loading bay in small loads.
  • Old boards cut into shorter lengths on the scaffold before they go down the chute.
  • Materials delivered to the drive beside the scaffold, so they are not carried far.
Residual risk4 Lowlikelihood 2 × severity 2
HazardBad weather: high winds catching long lengths like a sail, or rain and ice making the boards slipperyWho might be harmedThe team, and people below if a length is blown offInitial risk12 Highlikelihood 3 × severity 4Control measures
  • Sam checks the forecast each evening and morning, and work on the scaffold stops in high winds, heavy rain or ice.
  • Long lengths are not handled on the scaffold when it is gusty.
  • Boards checked each morning and kept clear of debris, and nobody goes up on frosted or icy boards.
  • After high winds the scaffold is inspected by the scaffolding contractor before anyone uses it.
Residual risk4 Lowlikelihood 1 × severity 4
HazardCuts and injuries from the circular saw and hand tools, and from nails in the old timberWho might be harmedSam, Ellie and KofiInitial risk9 Mediumlikelihood 3 × severity 3Control measures
  • Cordless tools only, so there are no leads on the scaffold, with guards checked each morning.
  • Cutting done on trestles on the drive, inside the barriers, not on the scaffold boards.
  • Cut-resistant gloves for handling old timber and gutters, and safety glasses when cutting.
  • Nails pulled or bent over as the old timber comes off.
Residual risk3 Lowlikelihood 1 × severity 3

Likelihood × severity

Low 1–4Medium 5–9High 10–16Critical 17–25

How to fill in this risk assessment template

  1. Download the Word file and save a fresh copy for each job or activity. A risk assessment is about this work, in this place, with these people.

  2. Open the worked example alongside it, to see the level of detail to aim for.

  3. Fill in the details, the work and the people first, so the hazards you list belong to this job.

  4. Walk the site or watch the task, talk to the people who do it, and list the significant hazards in the table: things that could cause real harm, not every trivial risk.

  5. Score each hazard before controls: likelihood times severity, each from 1 to 5. Write the controls you will actually use, then score it again.

  6. If a risk is still high or critical after controls, change how the work is done or add controls before anyone starts.

  7. Brief everyone who does the work and have them sign the register. Review the assessment when the work, the site or the team changes, and after any accident or near miss.

More detail in our guide: How to adapt a risk assessment template before work starts

Risk assessment questions

Is a risk assessment a legal requirement in the UK?

Yes. Regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires every employer to assess the risks to their employees and to anyone else affected by their work, and the duty extends to self-employed people working in construction or whose work could put others at risk. If you employ five or more people, the significant findings must be written down. With fewer, you still have to assess the risks, and writing it down is the easiest way to show you have, which many clients and principal contractors will ask for anyway.

What should a risk assessment include?

What the work is and where, who made the assessment and when, the significant hazards, who could be harmed and how, the controls in place and any further action, a risk rating before and after the controls, the emergency arrangements, a review date, and a record of who was briefed on it. This template has a place for each. Keep it to the work in front of you: a short, specific assessment is more use than a long, generic one.

What are HSE's five steps to risk assessment?

Identify the hazards. Decide who might be harmed and how. Evaluate the risks and decide on the controls. Record your significant findings. Review the assessment and update it if necessary. The template follows the same order: the details and people sections cover the first two steps, the scored hazard table the third, the document itself is the record, and the review date and briefing register cover the last.

How do you score a risk on a 5 x 5 matrix?

Rate the likelihood of harm from 1 (rare) to 5 (almost certain) and the severity from 1 (negligible) to 5 (catastrophic, meaning death or permanent disability), then multiply them. In this template 1 to 4 is low, 5 to 9 medium, 10 to 16 high and 17 to 25 critical. Score each hazard before and after controls. The law asks for a suitable and sufficient assessment rather than a number, but scoring shows which risks need the most attention and whether your controls bring them down far enough.

Does HSE provide a risk assessment template?

Yes. HSE publishes a free risk assessment template, with example risk assessments for a few types of business, which suits a general assessment of a workplace. This template is set out for one job or activity: it adds the job details, the people at particular risk, a score before and after controls, emergency arrangements, a sign-off and a register for everyone briefed on it.

How often should a risk assessment be reviewed?

The law sets no fixed interval. Review it whenever there is reason to think it is no longer valid: when the work, the equipment, the site or the team changes, after an accident or near miss, or when workers raise a concern. For routine work that does not change, many businesses also set a review date, often once a year, so it is looked at even when nothing seems to have changed.